Unit 4 of 4 · BBA Sem 5

Unit 4: Network analysis & inventory control

Operation Research notes · PTU syllabus (BBA501-18)

3 min read3 topics8 exam questions
On this page
  1. Unit summary
  2. PERT and CPM: background and stages
  3. Earliest and latest times, critical path and float
  4. Inventory control
  5. Key terms
  6. Quick revision
  7. Important questions

Unit summary

Projects and inventories both need careful planning. This unit covers network analysis with PERT and CPM — background, stages and time calculations — and inventory control with its classification, the EOQ model and ABC analysis.

After this unit you can

  • Draw a project network and find earliest and latest times
  • Identify the critical path and floats
  • Compute PERT expected times and variances
  • Explain inventory classification, EOQ and ABC analysis

PTU syllabus topics

  • PERT/CPM background and development
  • stages in application
  • determination of earliest and latest allowable times
  • classification of inventory control
  • EOQ model
  • ABC analysis
ComparisonPERT vs CPM
PERT
CPM

Time estimates

Three: optimistic, likely, pessimistic

One, deterministic

Focus

Time

Time and cost trade-off

Suits

Research, new projects

Construction, repetitive projects

Expected time

(a + 4m + b) / 6

Single estimate

1

Topic 1

PERT and CPM: background and stages

  • CPM (Critical Path Method) was developed by DuPont (1957) for projects with known activity times.
  • PERT (Programme Evaluation and Review Technique) was developed for the US Navy's Polaris missile project (1958) for projects with uncertain times.
ProcessStages in network analysis
  1. 1

    Planning

    List activities and dependencies

  2. 2

    Draw the network

    Nodes (events) and arrows (activities)

  3. 3

    Estimate times

  4. 4

    Compute earliest and latest times

  5. 5

    Identify the critical path

  6. 6

    Schedule, monitor and control

2

Topic 2

Earliest and latest times, critical path and float

  • Forward pass: Earliest Start (ES) and Earliest Finish (EF = ES + duration); take the maximum EF at merging nodes.
  • Backward pass: Latest Finish (LF) and Latest Start (LS = LF − duration); take the minimum LS at bursting nodes.
  • Total float = LS − ES = LF − EF. Activities with zero float lie on the critical path — the longest path, which sets the project duration.
ComparisonPERT vs CPM
PERT
CPM

Time estimates

Three (optimistic, most likely, pessimistic)

One (deterministic)

Orientation

Event-oriented

Activity-oriented

Focus

Time

Time and cost (crashing)

Use

Research and new projects

Construction and repetitive projects

Key formulasPERT time
  • Expected time

    te = (a + 4m + b) / 6

  • Variance

    σ² = [(b − a) / 6]²

  • Project SD

    √(sum of variances on the critical path)

  • Probability of completion

    Z = (target − expected) / σ

3

Topic 3

Inventory control

Inventory classes: raw materials, work-in-progress, finished goods and spares. Inventory control balances ordering costs against carrying costs and avoids stock-outs.

Key formulasInventory formulas
  • EOQ

    √(2DS / H)

  • Reorder level

    Lead time × usage (+ safety stock)

  • Total cost

    (D/Q)S + (Q/2)H

Example

D = 4,800 units, S = ₹100, H = ₹6. EOQ = √(2 × 4,800 × 100 / 6) = √1,60,000 = 400 units.

ABC analysis classifies items by annual consumption value: A (about 10% of items, 70% of value — tight control), B (20%, 20%), C (70%, 10% — simple control).

Key terms

Critical path
The longest path with zero float
Float
Time an activity can be delayed without delaying the project
Expected time
PERT weighted average time estimate
EOQ
Order size minimising total inventory cost
ABC analysis
Classification of inventory by value

Quick revision

  • Forward pass → ES, EF; backward pass → LS, LF.
  • Total float = LS − ES; critical activities have zero float.
  • te = (a + 4m + b)/6; σ² = [(b − a)/6]².
  • EOQ = √(2DS/H); ABC: 10-20-70 items, 70-20-10 value.

Important exam questions

Practice questions written to the PTU exam pattern for this unit's syllabus: short answers (Section A style) and long answers (Sections B and C style).

Short-answer questions

  1. Q1.Differentiate between PERT and CPM.
  2. Q2.What is the critical path?
  3. Q3.Define total float.
  4. Q4.Write the PERT formula for expected time.
  5. Q5.What is ABC analysis?

Long-answer questions

  1. Q1.Draw a network, find the critical path and the floats of all activities.
  2. Q2.Solve a PERT problem and find the probability of completing the project by a target date.
  3. Q3.Explain inventory control with EOQ and ABC analysis.

Stuck on this unit?

Message SBS on WhatsApp for help with Operation Research, or to ask about studying BBA at Synetic.

WhatsApp us